Little Elm ISD trustees will get an update Monday, Nov. 16, on where the district's $289.5 million 2022 bond stands, as part of the monthly financial report on their consent agenda.
The capital projects summary, current through Sept. 30, breaks the package into four main pieces:
- High school renovations: $95.4 million spent of $164.55 million budgeted, or 52.4%.
- Lakewood Elementary: $48.1 million spent of $50.4 million, or 95.5%.
- Safety, technology, building upgrades and transportation: $20.8 million spent of $32.25 million, or 63.7%.
- Miscellaneous projects: none of the $42.3 million budgeted has been spent.
Together those four lines add up to the full $289.5 million, and spending across them comes to about $164.4 million, leaving roughly $125 million on the books.
Inside the $32.25 million upgrades category, two lines have passed their budgets. Safety and security work shows $10.2 million spent against $9.5 million, and transportation shows $1.05 million against $305,000. Technology is at $1.19 million of $7 million, and interior and exterior upgrades at $8.38 million of $15.45 million.
The report does not explain the overruns or say what the miscellaneous money is meant for.