Next Spiritas Ranch phase would add $2,100 to $2,400 a year in PID payments on 145 new homes

The Town Council sets a Dec. 15 hearing Tuesday on $3.4 million in assessments to repay the developer for roads, drainage and utilities in Improvement Area 3, on top of PID charges already on the land.

Tessa Cho· AI-assisted, edited by Jake Team

November 11, 20262 min read

Buyers of 145 homes planned in the next section of Spiritas Ranch would pay off part of the cost of their streets, pipes and drainage through special assessments of about $22,000 to $25,000 per house, under a plan the Little Elm Town Council takes up Tuesday, Nov. 17.

The resolution, a regular agenda item, accepts a preliminary service and assessment plan for Improvement Area 3 of the Spiritas Ranch Public Improvement District and calls a public hearing for Dec. 15. The council would vote on actually levying the assessments after that hearing. Economic Development Corporation Executive Director Jennette Espinosa is the staff contact, and staff recommend approval.

What gets built

Improvement Area 3 covers about 31 acres, labeled phase 2M, with 74 homes on 50-foot lots and 71 on 40-foot lots. The project engineer's estimates put the public improvements at $5,420,115:

  • Roads and right-of-way: $2,469,314
  • Storm drainage: $1,300,138
  • Sanitary sewer: $426,645
  • Water: $396,999
  • Engineering, district formation and other soft costs: $827,019

The town would own and maintain the roads and drainage. The plan says the water and sewer lines will be owned and operated by MSUD.

Who pays

Assessments on the 145 lots would cover $3,398,000, with $2,102,115 from other sources. An extra $80,000 covers levy fees and the first year of administration. The developer, MM Little Elm 548 LLC, would pay for the work up front and be reimbursed with interest, but only from the assessments collected in Improvement Area 3, under a reimbursement agreement the plan dates to Dec. 15.

The assessment would be $24,867 on a 50-foot lot and $21,941 on a 40-foot lot. Spread over the life of the debt, the plan projects average yearly installments of $2,433 and $2,147. Using developer-supplied home values of $425,000 and $375,000, that works out to about 57 cents per $100 of home value, roughly what a property tax rate of that size would cost.

These lots already carry shares of two earlier Spiritas Ranch PID assessments for the district's major improvements. Counting all three, the plan puts the combined annual installment at about $3,669 for a 50-foot lot and $3,136 for a 40-foot lot, or about 84 to 86 cents per $100 of value.

The bigger district

The council created the PID on Feb. 2, 2021. It spans about 545 acres and is now expected to hold 2,171 single-family homes, according to the plan. Improvement Area 1 has 1,057 homes and Area 2 has 327 homes plus two acres of retail.

Sources

destinyhosted.com

destinyhosted.com

Share

Tessa Cho· AI-assisted, edited by Jake Team

Tessa Cho writes about community life, schools, public safety, and local events in Little Elm.

Related Stories

More in Texas