AUSTIN, Texas — The Public Utility Commission of Texas approved ERCOT’s new “Batch Zero” large-load interconnection framework on June 18, 2026, launching the state’s first systematic attempt to manage an unprecedented 438-gigawatt queue of projects seeking to connect to the Texas power grid, nearly 90% of which are data centers.
Little Elm, a city of approximately 55,000 in Denton County along the south shore of Lewisville Lake about 35 miles north of Dallas, boasts 23 miles of shoreline and rapid suburban growth.
The 438 GW tracked by ERCOT represents more than five times the grid’s all-time peak demand of 85,508 megawatts, set in August 2023. ERCOT’s own forecasts had projected peak load reaching 367,790 MW by 2032, driven by more than 250,000 MW of large-load requests. However, ERCOT officials acknowledged those forecasts are likely inflated, as many projects in the interconnection queue are speculative and may never be built.
Under the new Batch Zero process, ERCOT will study groups of large projects simultaneously rather than evaluating each one individually. Only projects that meet a “maturity criteria”—having secured financing and land—will be eligible for the first batch, with inclusion decisions expected by August 2026. A final transmission plan for Batch Zero is slated for fall 2027, and a second round of applications will open in summer 2027.
“Texas is experiencing an energy transformation unlike anything we have seen before. This new process represents a fundamental shift in how ERCOT manages the significant growth of large load interconnection, providing a structured, transparent path forward.” — Pablo Vegas, ERCOT President and CEO



